Jarszewo Wind Farm is moving forward

Jarszewo Wind Farm is moving forward

13 May 2026

Jarszewo Wind Farm is moving forward

Construction

As part of the Jarszewo Wind Farm project, developed by Futureal Group, we are responsible for delivering key power infrastructure and the grid connection process, including the construction of:
🔹 30/110 kV Jarszewo GPO substation,
🔹 110 kV high-voltage transmission line connecting the substation with the Recław GPZ.

The project has now entered an advanced stage, with major infrastructure milestones being completed:
✔️ civil works completed (foundations for HV and MV equipment, as well as the substation building),
✔️ protection, communication and telemechanics cabinets installed,
✔️ MV switchgear delivered,
✔️ installation of HV equipment and primary & secondary circuits currently underway.

Each of these stages brings the facility closer to full technical readiness for safe integration into the national power system and power evacuation from the wind farm.⚡