Boldekow substation energized!

Boldekow substation energized!

23 May 2025

Boldekow substation energized!

New realization

The 110/33 kV Umspannwerk Boldekow substation is a heart of the Solarpark Boldekow / PV Boldekow – an investment by Iberdrola Deutschland, one of the world’s leading companies in the renewable energy sector.

P&Q was responsible for:
✔️ execution of civil and electrical works,
✔️connecting the substation to the German distribution network (DSO: E.DIS),
✔️ performance of executive designs, including all necessary arrangements and coordination with the grid operator,
✔️ complete commissioning and energization of the substation.

This is a crucial step in our expansion into the German market and proves that our competence in delivering high-quality energy infrastructure is recognized internationally.

We would like to thank all individuals and teams who contributed to the success of this project:
🔧 Execution team: Paweł Niewiadomski, Denys Vlasov, Marcin Chybowski, Dominik Mieczkowski, Milena Dąbrowska, Iryna Vlasova, Hubert Panasewicz,
📐 Design team: Bartosz Giza, Marcin Maksymik, Artur Adamik, Michał Rzońca.
💼 Back Office team and everyone else involved – thank you!

This is just the beginning of our journey in Germany – with more challenges and exciting renewable energy projects ahead!

robert
Posts made: 96